Urgent Planned Maintenance Notification - 2nd April 2017

  • Friday, 31st March, 2017
  • 17:00pm

Dear Valued Customer,

Greetings from ModernOne.

Please be inform that we have to postpone the urgent planned maintenance to new date/time.

Start Date/Time

:

2nd  Apr 2017 00:01hrs (GMT+8)

End Date/Time

:

2nd Apr 2017 06:01hrs (GMT+8)

Planned event duration

:

6 hours

Service Impact

:

15 minutes downtime (for reboot) and 1 hour of intermittent downtime within the stipulated maintenance window.

Reason

:

Upgrade the trunk switch’s firmware to fix software bug.

Planned Maintenance Activity

:

1. Upload latest firmware into switch.

2. Perform reboot the switch to load the new firmware.
3. Perform failover test.


We apologize in advance for all inconvenience causes, please do not hesitate to contact us via email at support@nocser.net if you have any questions or concerns about this emergency maintenance activity.

Your co-operation is highly appreciated.


Thanks & Regards,
ModernOne Data Solutions Sdn Bhd